Three Chopt Rd Reconnection

About

The project will reconnect Three Chopt Rd under Route 288. Three Chopt Rd was disconnected when Route 288 was built, creating two dead end cul-de-sacs. By reconnecting Three Chopt Rd under Route 288, it provides more direct access from the Ashland Rd Interchange to Short Pump via Three Chopt and Broad St.

Timeline

  • Preliminary Engineering: 2025-2026
  • Right of Way Acquisition: 2028-2029
  • Construction: 2030-2032